#6 Reconcile PMR permits and the stored equipment list

Aperto
aperto 4 anni fa da g0dub · 1 commenti
g0dub 4 anni fa ha commentato

A condition of PMR permits is that groups provide a list of equipment to be used. Over time this seems to have slipped. Need to identify issues by zone for next CoM meeting.

A condition of PMR permits is that groups provide a list of equipment to be used. Over time this seems to have slipped. Need to identify issues by zone for next CoM meeting.
g0dub added the
Regulatory
label 4 anni fa
g0dub la data di scadenza 2020-08-25 è stata aggiunta 4 anni fa
g0dub rimossa la data di scadenza 2020-08-25 4 anni fa
g0dub 4 anni fa ha commentato
Proprietario

Challenging permit renewals as they come in.

Challenging permit renewals as they come in.
Effettua l'accesso per partecipare alla conversazione.
Nessuna milestone
No Assignees
1 Partecipanti
Data di scadenza

Nessuna data di scadenza impostata.

Dependencies

This issue currently doesn't have any dependencies.